Critical Path Analysis of an Automotive Engine Laboratory Construction Project
DOI:
https://doi.org/10.54783/influencejournal.v8i2.362Keywords:
Critical Path Method, Construction Scheduling, Project Control, Total Float, Activity-on-Node.Abstract
Construction schedules presented only as bar charts provide limited information on logical dependencies, time flexibility, and the activities that govern project completion. This study evaluates the schedule of an automotive engine laboratory construction project using the Critical Path Method (CPM). Case data were consolidated from schedule documents, field observations, interviews, and project documentation into eleven work activities and one completion milestone. An Activity-on-Node network was developed and evaluated through forward-pass, backward-pass, and total-float calculations. The CPM model produced a 17-week project duration, equal to the company's original target, while revealing two critical paths: A-B-C-D-I-J-L and A-B-C-D-I-K-L. Steel erection and roofing each had two weeks of total float, whereas wall work and painting each had one week. Seven of the eleven executable activities were critical, and the two critical paths shared a 13-week common sequence. These findings demonstrate that CPM contributes not only through schedule compression but also by exposing schedule logic, focusing managerial attention, and identifying near-critical work that can become critical after a small deviation. The model is deterministic and does not incorporate resource constraints; therefore, subsequent schedule development should integrate resource leveling and probabilistic risk analysis.
References
Dalouchei, F. (2022). A bi-objective model for scheduling construction projects using critical chain method and interval-valued fuzzy sets. Buildings, 12(7), 904. https://doi.org/10.3390/buildings12070904
Gaspar, D. J., George, A., McCormick, R. L., & Wagner, R. M. (2022). Building and Executing Aggressive Research Plans in a Large National Laboratory Consortium: Insights from the Co-Optimization of Fuels and Engines Initiative. Pacific Northwest National Laboratory (PNNL), Richland, WA (United States).
Habibi, I. (2023). Penerapan Critical Path Method pada penyelesaian proyek rehabilitasi Jalan Parigi Lama di Kabupaten Sumedang. Go-Integratif: Jurnal Teknik Sistem dan Industri, 4(1), 1–10.
Hasan, M. (2024). Mitigating project schedule risks by identifying subcritical paths and variance-critical activities. Journal of Construction Engineering and Management, 150(8). https://doi.org/10.1061/JCEMD4.COENG-14821
Husna, R. A. A. (2022). Implementasi CPM dan PERT dalam memprediksi durasi serta biaya pembangunan Musala Al-Ikhlas di Kotawaringin Barat. Focus ACTion of Research Mathematic, 5(1), 97–109. https://doi.org/10.30762/f_m.v5i1.633
Institute, P. M. (2019). Practice standard for scheduling. Project Management Institute.
Institute, P. M. (2021). A guide to the Project Management Body of Knowledge (PMBOK guide) and the standard for project management. Project Management Institute.
Jaber, H., Marle, F., Vidal, L.-A., & Didiez, L. (2018). Criticality and propagation analysis of impacts between project deliverables. Research in Engineering Design, 29(1), 87–106.
Kammouh, O. (2022). Dynamic control for construction project scheduling on-the-run. Automation in Construction, 141, 104450. https://doi.org/10.1016/j.autcon.2022.104450
Kim, K. (2020). Generalized resource-constrained critical path method to improve sustainability in construction project scheduling. Sustainability, 12(21), 8918. https://doi.org/10.3390/su12218918
Kostrzewa-Demczuk, P. (2024). Construction schedule versus various constraints and risks. Applied Sciences, 14(1), 196. https://doi.org/10.3390/app14010196
Lee, S., & Shvetsova, O. A. (2019). Optimization of the technology transfer process using Gantt charts and critical path analysis flow diagrams: Case study of the korean automobile industry. Processes, 7(12), 917.
Marit, I. Y., Nursanti, E., & Vitasari, P. (2020). Critical path method to accelerate automotive maintenance duration. International Journal of Scientific & Technology Research, 9(03), 6777–6782.
Pantis, I. T., Seica, A. V, & Blaga, F. S. (2024). Management of the relocation project of a production line using the critical path method. Annals of the University of Oradea: Facsicle of Management & Technological Engineering, 32(2).
Saputra, N. (2021). Analisa penjadwalan proyek dengan metode Critical Path Method (CPM): Studi kasus pembangunan gedung rawat inap RSUD Abdul Manap Kota Jambi. Jurnal Talenta Sipil, 4(1), 44–52. https://doi.org/10.33087/talentasipil.v4i1.48
Sholahuddin, M. (2024). Penerapan Critical Path Method (CPM) pada proyek rekonstruksi jalan untuk mengidentifikasi kegiatan pekerjaan jalur kritis. DEARSIP: Journal of Architecture and Civil, 4(2), 72–84. https://doi.org/10.52166/dearsip.v4i02.7822
International Organization for Standardization. (2020). ISO 21502:2020, Project, programme and portfolio management - Guidance on project management. ISO.
Ulfa, S. (2021). Implementasi metode Critical Path Method pada proyek Synthesis Residence Kemang. Jurnal Optimasi Teknik Industri, 3(1), 1–6. https://doi.org/10.30998/joti.v3i1.4167
Downloads
Published
How to Cite
Issue
Section
License
Copyright (c) 2026 INFLUENCE: INTERNATIONAL JOURNAL OF SCIENCE REVIEW

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.














